Recent Progresses
The ten-year construction of
the TGP has been carried out smoothly and the construction quality
has well satisfied the design requirement.
By March 25, 2003, the main civil work quantities accomplished
are:earth-rock excavation 1,341.4 million m3 ( amounting to 99.34%
of the total work quantities);earth-rock backfill 33.93 million m3
(amounting to 78.13% of the total work quantities); concrete palcement 204.9 million m3 (amounting to 70.91 % of the total work
quantities).
In the past ten years,the funds needed has been well put in place
and the project construction has progressed smoothly.The project
construction has been carries out according to the approved
general schedule and a little bit ahead of time.The investment for
the project has so far been controlled within the approved
budgets,of which 41.55 RMB billion yuan on the main structure, RMB
37.67 billion yuan in the reservior resettlement and RMB 11.8
billion yuan in interest for loans and price escalation have been
completed .
According
to the investigation,all in total 1.13 million people need to be
relocated, 36.88 million m2 housing need to be rebuilt and 1,599
factories and enterprises need to be demolished and rebuilt.By the
end of December,2002, the moving of 709.2 thousand migrants has
been completed and 25.38 million m2 housing of various kinds has
been rebuilt, 1,097 factories and enterprises have been moved and
rebuilt. Howerver,the current status of the project's resettlement
has completely met the demands of the approved general schedule.
Since the beginning of the construction of the TGP, the tasks of
the 1st stage construction have been finished,including excavation
of the open diversion channel,building of the temporary shiplock
and the river closure of the main channel.In the 2nd stage
construction,the main tasks are the concrete placement of the dam
and the permanence shiplock,the metal work and the installation of
the generating units.Up to now, the concrete placement of the dam
sections has reached elevation of 120 m. The excavation work for
the lock chambers of the permanence shiplocks has been finished.In
Augest of 2003, the first group of the generating units will be
put into operation and the permanence shiplock will also be put
into use.
However,painstaking efforts should still be made, the project
erectors are fully implementing the policy of "Fine design,Careful
construction and Elaborate Organization", and above quota the
whole project are to be accomplished on time.

กก
Latest
The
Three Gorges reservoir officially began to store water on June
1,2003 as the sluice gate started to close at 00:00 that day.It is
a major step towards completion of the world's largest
hydroelectric project.
On June 16,2003, the third trial navigation of Three Gorges
Project was proved to be successfu as ships passed through the
permanence shiplock without hindrance .It marked the start of a 12
month-long trial navigation for the shiplock.
 |