Main tasks for the year of 2003
The main tasks for the year
of 2003 are as follows:
To insure that the diversion bottom hole will be dammed to
conserve water on time.
To insure that the shiplocks will open to navigation on time.
To insure that the first group of the generating units will be put
into operation on time.
To well organize the check and accept work of water conservancy,
experimental navigation and the preparation work before the first
group of the generating units being put into operation as well as
the flood-defensive work after the damming of water.

The implementation of the major projects for the year of 2003 are
schemed as:
Concrete placement: 1.87 million m3
Earth-rock excavation:3.39 million m3
Earth-rock fill:6.59 million m3
Installation of the metal configuration and built-in
components:22,136 ton
Generating units installation:16,625 ton
Built-in generating units£º838 ton
Asphaltum and concrete placement :5000m3

|