Three Times of Damming of the main channel of the TGP
T he
first is the damming of the main channel of the Gezhouba Water
Conservancy Project carried out on January 3rd,1981.Through the
hard work of the constructors,the dragon-mouth of the damming left
is 33.2 meters wide.The flood-discharge of the dragon-mouth is
4190 to 4720 m3/s while the maximum water fall is up to 3.23
meters. The current velocity is 7.1m/s at its extreme.The whole
damming took 36.4 hours in total.
The second is the damming of the main channel of the TGP which was
started on November 8th,1997.The dragon-mouth left this time is 40
meters wide.The actual flood discharge is 8,480 m3/s while the
maximum water fall is 1.24 meters. The fastest current velocity is
3m/s.The second damming of the main channel took 29 hours.
The third damming of the main channel began in December,2002.It
was carried out in the Diversion Ditch of the TGP.The big dragon
mouth closed on December 6th,2002.The dragon-mouth of the upper
banquette is 150 meters while the one of the lower banquette 140
meters.The designed flood-discharge is 10,300 m3/s while the
maximum water fall is 4.11m. The current velocity is 10 m/s at its
extreme.

|