7 |
Power Stations
According to the
scheme, two power plants will be placed at the toe of the dam, one
on each side. The total length of the power plant on the left is
about 643.6 m, with 14 sets of turbine generator units installed,
while that of the one on the right , 584.2 m in total length, 12
turbine generator units installed. Thus, there are 26 sets of
turbine generator units in total (the turbine is of Francis type)
, 700 MW for each, totaling 18,200 MW in installed capacity that
will produce 84.68 TW/h of electricity output annually. 500 kV AC
transmission lines will send electricity to Central China and the
east of Sichuan Province. 600 kV DC transmission lines will send
the electricity to East China. There are 15 transmission lines in
total.
On the right bank, enough room has been preserved for the future
underground power plant with 6 turbine generator units, 4,200 MW
of installed capacity. The intakes will be constructed
simultaneously with the project.

|