According to " The
Comprehensive Utilization Planning of the Yangtze Basin" approved
by the State Council, the Three Gorges Project is the key backbone
project for rehabilitation and development of the Yangtze River.
The main tasks of TGP are: regulating the floods from the upstream
reaches in Sichuan Province to control the floods or relief the
flood damage in middle and lower reaches of the Yangtze,
especially in the Jinjiang reaches; developing the hydro-power
resources in the Three Gorges reach to provide the central China,
east China and the east Sichuan Province (now the city of
Chongqing, the same as below) with huge amount of the electricity;
improving the navigation condition of the reaches between
Chongqing and Yichang.

กก
FLOOD CONTROL
The plain areas along the
middle and lower reaches of the Yangtze boast highly developed
industry and agriculture. Nevertheless these areas are most
vulnerable to floods and waterlogging, because the flood level can
be 6-17 meters higher than the ground level of the adjacent plains
and they are protected only by the 33,000- kilometer- long dykes .
Flooding has been very frequent since ancient times and the
reoccurence interval is about 10 years. This is easy to understand
because the flood-discharging capacity of the river channel from
Jingjiang to Wuhan,which is only 60,000-70,000 m/s,is far too
small to discharge the large floods as high as 110,000 m/s. The
Three Gorges Dam(TGD)can protect the downstream plain against the
biggest flood in 100 years and prevent devastating disasters from
occurring in case of the biggest flood in 1000 years,with the help
of the flood diversion structure.To avoid heavy losses caused by a
possible war, we can prelower the water level, because modern wars
always have signs. History will prove the project is the "Patron
Saint" ensuring the safety of lives and properties of more than 15
million people inhabiting the downstream areas and 1.53 million
ha. farmland as well as the Beijing -Guangzhou and Beijing-Jiulong
railroads.

กก
POWER GENERATION
After completion,the Yangtze
River water will be used to produce electricity first at Three
Gorges Power Station(TGPS) then regulated by the Gezhouba Project
for the purpose of navigation and finally reused for power
generation at the Gezhouba Power Station. Thus the total annual
output of the two stations is expected to reach 195 billion kwh
.When completed,the power output will generate a yearly net value
of 10 .5 billion yuan($ 1. 2billion) on the assumption that the
price of electricity is 0.1 yuan ($0.0114)per kwh, and an output
value of 525 billion yuan($60.3billion)on the assumption that 1
kwh of electricity can produce an output value of 5 yuan
($0.57),which can result in job opportunities for nearly 5.25
million people assuming that a yearly value of 10,000 yuan($1,149)can
be created per person.It should also be noted that the Project
enjoys a very advantageous geographical position ,being within
1,000 km of many industrial centers.it is expected to be the
network junction for graphical position,being within 1, 000 km of
many industrial centers.It is expected to be the network junction
for all the power grids in the country.When the grid goes into
operation, it will not only supplement the available thermal
power, hydro-power and nuclear power in the country, but also
upgrade the quality and efficiency of the grid, which will
certainly make the Project the national nerve centre-the