|
E
|
cological & Environmental Protection |
Page
|
|
2
|
|
4 |
5 |
6
|
7 |
Environmental Purification
After completion,the
TGP will have an annual electricity output of 85 billion kwh,which
is equivalent to a yearly saving of 50 million tons of coal,14
thermal power plants with an installed capacity of 1. 3 million kw
each and 3 coal fields with an annual 15 million tons as well as
an equivalent of the 800 km double-track railway from Qinhuangdao
to Datong,which would occupy a lot of farmland as well. The latter
alternative would leave us contending with a large amount of waste
water,waste gases and residues in addition to 120 million tons of
carbon dioxide,2 million tons of sulphide dioxide,10,000 tons of
carbon monoxide, 370,000 tons of compound oxygen and mitorgen a
year. All these show that the Project is an excellent
environmental purifier for the mankind .

กก
Research of Sediment
The
sediment issue of the TGP is one of the major technical problems
needing to be tackled. Since 1950's,many domestic research
institutes and a lot of famous sediment experts have conducted
extensive studies on this issue . The successful experience of
Gezhouba Hydroelectric Project on the sediment treatment has laid
solid foundation for the sediment study of the Three Gorges
Project.
Comprehensive research methods as prototype observation,
mathematical model computation, physical model tests, and analogue
analysis on existing projects have been adopted for the sediment
study of the project. The conclusion is that the sediment problem
of the TGP is resolvable based on the examinations and
authentication organized by sediment experts at home and aboard.
1. Sediment Load
According
to the observations of Yichang Hydrologic Station over 40 years,
the sediment discharge of suspended load on average is about 526
million tons a year, with median diameter of 0.033 mm. The annual
bed load is about 8.6 million tons, including 0.76 million tons of
cobbles, which takes up only a small proportion of the total
sediment load.
The water discharge at TGP' s dam site is large, reaching 451
billion m3 annually with average sediment rate only about 1.2
kg/m3, whereas, the sediment discharge at Sanmenxia Project on the
Yellow River is 1.6 billion tons with average sediment load of 37
kg/m3. The water discharge at the TGP dam site is 10 times that at
Sanmenxia Project, but the annual sediment load is only one third
of it. Therefore, the sediment problem of the Yangtze River is
quite different in nature from that of the Yellow River.
In recent years, some experts deemed that the sediment yield in
the Yangtze River is in a tendency of increase based on the data
of the early 1980's. However, it is not a fact. According to the
long term observation and checking results, the sediment load in
the Yangtze River changes periodically below or above the average
level on a random basis, and there is no obvious tendency of
increase. The value of sediment load at the dam site was far below
the average several times in the late 1980's and early 1990's.
This is an evident proof.

2. Permanent Use of the Reservoir
The
Yangtze River has abundant runoff. The Three Gorges Dam is to be
equipped with 23 bottom discharge outlets with low elevation (90
m) and large dimension (7x9 m) . Meanwhile, the reservoir level in
the flood season will be maintained at a fairly low elevation (145
m) . These two characteristics allow the application of a strategy
of reservoir operation summed up in China as "discharging the
turbid and impounding the clear". During the flood season from
June to September, when the river carries 84 % of the annual
sediment load and 61% of the annual runoff, the reservoir draws
down to FCL (145 m) that creates a condition in favour of sediment
sluicing, letting a large discharge of sediment out of the
reservoir from the bottom outlets. At the end of the flood season
(October) when there is less sediment content in water, the
reservoir will be impounded to NPI. (175 m) for enhancement of
power generation and navigation. In this operation manner, most of
the sediment will be moved out, the large part of the deposit of
sediment will remain in the dead storage of the reservoir, and
most part of effective storage can be preserved permanently.
The length of the TGP reservoir is over 600 km and the average
width is only about 1,100 m. It looks like a ribbon in the plain.
So it is still a river, and not a lake-like reservoir. The whole
reservoir is quite uniform in width and for the most part less
than 1,000 m wide, only one seventh of the reservoir is about
1,000 to 1,700 m wide.The morphology of the reservoir is
favourable for the removal of sediment . Since the estimated width
of the equilibrium channel corresponding to the hydrological
conditions of the TGP reservoir is 1,300 m little flood plain is
expected to be formed along the main channel in the TGP reservoir.
Thus, large percentage of effective storage can be preserved
permanently.
The deposition in the TGP reservoir has been analyzed numerically
by mathematical models. The result is quite satisfactory.
According to the calculation results, after a century operation
when the reservoir sedimentation already comes to the balanced
state, the reservoir's effective storage capacity could still
remain at 86-92%.
It is believed that the conclusions are reliable, not only because
the mathematical model is developed in a large number of
researches and observations and verified by many experts at home
and abroad, but also it is based on several successful engineering
practices.

|